To Complete Performance Index (TCPI)

The To Complete Performance Index (TCPI) calculates the cost efficiency required on remaining work to finish within a target budget. Learn the TCPI formula and how to interpret whether the required efficiency is achievable.

How TCPI Works

TCPI is the inverse of forecasting: instead of predicting where the project will end up, it calculates the cost efficiency the team must achieve on remaining work to hit a specific budget target. It answers the question: given what we have spent so far, how efficiently must we work from now on to finish within budget?

The formula is TCPI = (BAC minus EV) / (BAC minus AC) when targeting the original budget, or TCPI = (BAC minus EV) / (EAC minus AC) when targeting the revised estimate at completion. The numerator is the remaining work (in budgeted terms). The denominator is the remaining budget (in dollar terms).

A TCPI of 1.0 means the team must maintain the originally planned efficiency. Greater than 1.0 means the team must work more efficiently than planned to stay on budget. Less than 1.0 means the team can afford to be less efficient and still finish within the target.

Interpreting TCPI

The critical question is whether the required TCPI is achievable. A TCPI of 1.05 means the team needs to be 5% more efficient than planned, which is often achievable through process improvements or scope adjustments. A TCPI of 1.20 means the team needs to be 20% more efficient than planned, which is rarely achievable without significant scope reduction. A TCPI above 1.30 is a strong signal that the original budget is unrecoverable.

When TCPI against the original BAC is unrealistic, calculate TCPI against the EAC instead. This tells the team what efficiency is needed to hit the revised forecast, which may be more achievable.

When to Use TCPI

Calculate TCPI whenever EAC exceeds BAC and the sponsor is asking “can we still finish on budget?” TCPI provides an objective, mathematical answer. If the required TCPI is above 1.20 to 1.30, the honest answer is almost certainly no. Present TCPI alongside CPI and EAC to give stakeholders the complete cost picture: where we have been (CPI), where we are headed (EAC), and what it would take to change course (TCPI).

When TCPI Is Less Useful

TCPI is meaningless at the start of a project (no actual cost data) and becomes increasingly meaningful as the project progresses and more budget has been consumed. It is a mid to late project metric. In the first 20% of a project, focus on establishing accurate CPI data rather than calculating TCPI.

Commonly Confused With

TermKey Difference
CPI (Cost Performance Index) CPI measures past cost efficiency (what happened). TCPI measures required future efficiency (what must happen). CPI is descriptive. TCPI is prescriptive.
EAC (Estimate at Completion) EAC predicts the final cost based on current trends. TCPI calculates the efficiency needed to hit a target cost. EAC is a forecast. TCPI is a target.
ETC (Estimate to Complete) ETC is the predicted cost of remaining work in dollars. TCPI is the efficiency ratio required on that remaining work. ETC answers how much more money. TCPI answers how efficiently that money must be spent.
Use formula Custom Fields to calculate TCPI automatically and display it alongside CPI and EAC on your project Dashboard.
Calculate TCPI in ClickUp

Common Questions About To Complete Performance Index (TCPI)

What is the TCPI formula?
TCPI = (BAC minus EV) / (BAC minus AC) when targeting the original budget. The numerator is the remaining work value. The denominator is the remaining budget. A result above 1.0 means the team must work more efficiently than planned to finish on budget.
What does a TCPI of 1.25 mean?
A TCPI of 1.25 means the team must achieve $1.25 of earned value for every $1.00 spent on remaining work to finish within the original budget. This requires 25% greater efficiency than planned and is generally considered unachievable without significant scope reduction.
At what TCPI value should I recommend a budget revision?
When TCPI against the original BAC exceeds 1.20 to 1.30, the original budget is almost certainly unrecoverable through efficiency improvements alone. Present the TCPI data to the sponsor alongside CPI and EAC and recommend a budget revision, scope reduction, or both.